The Pulichintala Project is a multi-purpose water management project for irrigation, hydropower generation, and flood control in the state of Andhra Pradesh, India.[3] It is a crucial irrigation facility for farmers in four coastal districts: West Godavari, Krishna, Guntur, and Prakasam, covering over 13 lakh acres. It has 24 gates and a balancing reservoir with a capacity of 46 Tmcft at 175 feet (53 m) MSL full reservoir level (FRL).[3]

Pulichintala Project
Location of Pulichintala Project in Andhra Pradesh
Official nameK.L Rao Sagar
CountryIndia
LocationPulichintala village, Bellamkonda, Guntur district, Andhra Pradesh[1]
Coordinates16°45′15″N 80°03′24″E
PurposeIrrigation & Water supply
Construction began08 August 2009
Opening date7 December 2013
Construction cost1850 crore rupees
Owner(s)Government of Andhra Pradesh
Operator(s)Andhra Pradesh
Dam and spillways
ImpoundsKrishna River
Height42.24 m
Length2,922 m
Width (base)31 m
Spillway typeControlled
Spillway capacity10 lakh cusecs
Reservoir
CreatesPulichinthala Reservoir
Total capacity46 Tmcft
Active capacity36.23 Tmcft
Catchment area240,732 km2
Surface area144 km2
Operator(s)APGENCO[2]
Commission dateSeptember 22, 2016 (2016-09-22)
Hydraulic head25 Meters
Turbines4 × 30 MW Kaplan turbine
Installed capacity120 MW
Website
irrigationap.cgg.gov.in/wrd/dashBoard

History


In 1911, British engineer Col. Ellis proposed an irrigation project upstream of the Prakasam Barrage. At the time, the British government showed little interest in the proposition.[4] Later, the Raja of Muktyala led the push for the Pulichintala Project with the help of Moturi Satyanarayana and K.L Rao.[4][5][6] It was the first project to start under the ambitious Jalayagnam program in the year 2004. https://irrigationap.cgg.gov.in/wrd/static/approjects/KLRaoProject.html Financial tie-up happened in 2009 and commenced in 2009.

On 7 December 2013, the project was ready for a trial run,[7] and it started impounding water in August 2014.[8] It was fully completed in September 2018.[9] The total cost of the project has exceeded Rs.1850 crores.


Project


The irrigation facility is in the Pulichintala village, located in the Guntur district near the Krishna River.[10] It is between the Vykuntapuram barrage (near Amaravati) and the Nagarjuna Sagar dam.[11] It has a 30 Tmcft live storage capacity to impound river floodwaters generated from the catchment area located downstream of Nagarjuna Sagar Tail Pond. The project reservoir provides a water supply to downstream Prakasam Barrage that then can be sent out through the Pattiseema lift/Polavaram irrigation canal during monsoon months.

The Vellatur lift irrigation scheme (constructed near 16°42′44″N 80°00′29″E), irrigates 13,000 acres in the Nalgonda district. It draws water from the Pulichintala reservoir.[12] The lift can pump water from 120 feet (37 m) MSL when the reservoir's gross storage is as low as 4 Tmcft. The proposed Yadadri Thermal Power Plant would also draw water from the reservoir.


Godavari Penna River Linking


The Godavari Penna River linking project was constructed to stabilize the existing irrigated area under the Nagarjuna Sagar right canal. The new lift would have greenfield alignment, and its first phase consists of five-step ladder pumping stages that transfer 7,000 cusecs of Godavari River water from Prakasam Barrage to deliver 73 Tmcft of Godavari water into the Nagarjuna Sagar right canal near Nekarikallu.[clarification needed]

With FRL 25M the newly created Vykuntapuram Barrage pond will have backwaters beyond Pokkunuru up to the toe of the Pulichinthala Project. It is more economical to construct the first stage pump house to lift water from the Prakasam Barrage backwater into the newly created Vykuntapuram Barrage pond and the second Lift stage from the Vykuntapuram Barrage pond to the existing K.L Rao Sagar Pulichintala Project and later lift Stages from K.L Rao Sagar to Nagarjuna Sagar right canal. It will shorten the length of this lift project canal, Pressure Main and fewer lift stages and also enable to lift of water up to Srisailam Project via the existing Reversible Reverse turbine pump houses in Nagarjuna Sagar Dam and its tail pond project. It is even more economical if the construction of a new gravity canal from Ibrahimpatnam to Vykuntapuram Barrage pond to deliver the Polavaram right main canal/ Budameru diversion canal waters directly into the Vykuntapuram barrage pond since Polavaram right main canal level is 33 m MSL at Ambapuram hill near Vijayawada.

A low-level, lift canal from the Krishna river located near 16°42′50″N 80°08′24″E at 20 metres (66 ft) MSL in the downstream of Pulichintala dam will be executed to feed Godavari water diverted from Polavaram Dam to some of the existing command area (situated below 60 m MSL) under Nagarjuna Sagar right bank canal to facilitate the extension of Nagarjuna Sagar right bank canal connecting Kandaleru feeder canal / Somasila Dam reservoir serving irrigation needs in Prakasam, Potti Sriramulu Nellore and Chittur districts including Chennai drinking water supply. A branch from this lift canal is also extended up to Pulichinthala dam (FRL 53.34 m MSL) to store Godavari water in Pulichintala reservoir during drought years and to irrigate lowlands along Krishna river up to Pulichintala dam.[13]


See also



References


  1. "K L Rao Sagar". Ap Irrigation Department. 12 January 2013. Retrieved 13 August 2019.
  2. "Status of Hydro Electric Projects under Execution for 12th Plan & beyond" (PDF). Archived from the original (PDF) on 15 July 2014. Retrieved 30 June 2014.
  3. "Pulichintala D06327". Retrieved 30 June 2014.
  4. Jonathan, P. Samuel (8 December 2013). "Pulichantala dedicated to nation". The Hindu. ISSN 0971-751X. Retrieved 14 July 2021.
  5. Rao, K. L. (1978). Cusecs Candidate: Memoirs of an Engineer. Metropolitan. p. 31.
  6. "Pulichintala project to water Prakasam barrage ayacut - Times of India". articles.timesofindia.indiatimes.com. Archived from the original on 27 November 2013. Retrieved 17 January 2022.
  7. "Pulichintala project on August 15 | Deccan Chronicle". www.deccanchronicle.com. Archived from the original on 15 July 2013.
  8. "Engineers complete trial run of Pulichintala Project". The Times of India. Retrieved 16 August 2014.
  9. AP Govt Plans to Develop Pulichintala Project as Tourist Place | Pulichintala Project | AP24x7, retrieved 19 January 2020
  10. "Pulichintala project progress report, APGenCo". Retrieved 15 May 2013.
  11. Srinivas, Rajulapudi (14 February 2019). "Naidu lays foundation stone for barrage across Krishna". The Hindu. ISSN 0971-751X. Retrieved 1 March 2019.
  12. "KCR, Harish Rao lying on Pulichintala issue: Uttam". Retrieved 28 September 2016.
  13. "Pulichintala, a capital saviour". Retrieved 7 September 2016.





Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2024
WikiSort.org - проект по пересортировке и дополнению контента Википедии