geo.wikisort.org - Reservoir

Search / Calendar

Lake Palmer was a man-made lake in Nashville between 16th Ave and 17th Ave, south of Hayes St and north of West End Ave.[4] This was the proposed location of a long-mooted mixed-use construction project near downtown Nashville that failed to materialize for over ten years.[5] Conceived by Nashville-based Alex S. Palmer & Company, the project was originally planned to open in 2007 as the West End Summit, a $300 million project for office space and apartments.

Lake Palmer
Lake Palmer
Lake Palmer
Location1600 West End Avenue
Nashville, Tennessee
United States
Coordinates36.1545°N 86.7935°W / 36.1545; -86.7935
Built2005 (2005)
Max. length400 feet (120 m)
Max. width300 feet (91 m)
Average depth60 feet (18 m)
Broadwest
General information
StatusProposal
TypeMixed use
Cost$490 million USD
OwnerPropst Development
Height
Roof406 ft (124 m)
Technical details
Floor countResidential/hotel tower, 34 stories;
office tower, 21 stories, 510,000 sq ft (47,000 m2);
retail/office building, 125,000 sq ft (11,600 m2)
Floor area900,000 sq ft (84,000 m2).
Design and construction
ArchitectKendall/Heaton Associates Inc.
Duda/Paine Architects
Cooper Carry
DeveloperPropst Development, Chartwell Hospitality
Structural engineerStanley D. Lindsey & Associates
Main contractorBovis Lend Lease (2006-2008)

Turner Construction Company (2013–2017)[1] Batson-Cook Construction (2017–2018)[2]

Turner Construction Company and Hoar Construction (2018–)[3]

Excavation initially started in 2005, but the project stalled as the developer attempted to cope with the credit crunch and sought an anchor tenant for the office portion of the project.[6] The resulting lake was a source of water for swimming pools and country clubs during water restrictions following the 2010 Tennessee floods.[7] The construction proposal was relaunched in September, 2012 with news that Nashville-headquartered Hospital Corporation of America (HCA) had signed leases to occupy two office towers on the site. In addition to the office towers, an InterContinental Hotel was planned as part of the development. After plans stalled, the property was sold to Propst Development in March, 2018.[7]

The site remained a massive, block-long excavation that was commonly called Lake Palmer, as this 85-foot-deep (26 m) hole was mostly filled with water.[8] As of September 2019, the lake was still visible on Google Maps and labelled as Lake Palmer.[9]


West End Summit


On September 27, 2012, Nashville Mayor Karl Dean, Gov. Bill Haslam, and HCA Chairman and CEO Richard Bracken, jointly announced the location of two corporate headquarters divisions of HCA at the site.[10] The proposed development was to include two towers of approximately 20 stories each, with a total floor area of 900,000 sq ft (84,000 m2). The corporate headquarters of Parallon Business Solutions would anchor one tower, and the other would be anchored by Sarah Cannon Research Institute (SCRI). The rainwater was completely drained (mostly into the street) in 2013 for the anticipated construction of the HCA building.

More than a year after HCA signed leases, construction had failed to start due to Alex S. Palmer & Company being unable to obtain equity financing for the $275 million project. In December 2013, HCA withdrew from the project, opting to build its own campus on a nearby site in Nashville's North Gulch district. The excavation filled back up with water.

Intercontinental Hotels withdrew their 12-story hotel proposal in February 2016.[11] The lake was again temporarily drained in March 2016, although no further proposal was revealed.[12]


Criticism


The failed West End Summit project, along with developer Alex S. Palmer & Company, faced public and media scrutiny because of its numerous construction delays, financing woes and construction liens.[13] Harmon Inc. filed a lawsuit stating it was owed US$120,000 by Alex S. Palmer & Company and Bovis Lend Lease for engineering services related to the project.[14]


Broadwest


On March 23, 2018, Huntsville, Alabama-based Propst Development announced they had purchased Lake Palmer for $36.9 million.[15][16] The announcement did not include detailed plans for the site.[17] Propst Development principal Chris Brown stated on June 27, 2018, that the mixed-use project would include a hotel and condos in a tower as high as 40 stories, and that another tower would include at least 500,000 sq ft (46,000 m2) of office space. Turner Construction Company returned jointly with Hoar Construction as contractors, and Cooper Carry was named as the firm providing architecture for the renamed "Broadwest" project.[3] On August 20, 2018, Brown told the Nashville Business Journal that the residential tower would be 34 stories and the office tower would be 21 stories, with a projected cost of $490 million entirely funded by the Propst family and Chartwell Hospitality, a hotel operator based in Franklin, Tennessee. The hotel in the residential tower would open in 2021 with 245 rooms, and be owner-operated by Chartwell Hospitality.[18] The plan included a park, and 2,500 vehicle parking spaces. Construction was expected to start in the fall of 2018.[19]

The first of four tower cranes was erected in March 2019. The 21-story office tower is planned to open in February 2021, and the 34-story residential tower is planned to open about six months later.[20]


See also



References


  1. "Palmer selects Turner to serve as WES general contractor". Nashville Post. Nashville, TN: SouthComm Inc. January 25, 2013. Archived from the original on March 10, 2013.
  2. "Real estate notes: Permit issued for demo of old convention facility". Nashville Post. May 9, 2017. Retrieved November 13, 2017.
  3. Sichko, Adam (June 29, 2018). "Two towers, new name for West End Summit". Nashville Business Journal. American City Business Journals. Retrieved July 2, 2018.
  4. "Government-issued Permit naming location as Lake Palmer". Retrieved December 22, 2016.[permanent dead link]
  5. Fox, Matt. "Best Accidental Lake". Nashville Scene. Retrieved November 13, 2017.
  6. Sisk, Chas (November 6, 2008). "Firm sues West End project developer over payment". The Tennessean. Retrieved January 8, 2009. [dead link]
  7. Lind, J.R. (26 March 2018). "Lake Palmer Sold: Languishing Development Gets New Owner". Patch. Retrieved 2 May 2018.
  8. "How Nashville West End Summit Became Lake Palmer". Nashville Real Estate. October 4, 2009. Retrieved June 7, 2010.
  9. "Lake Palmer, Tennessee 1, Nashville, TN". Google Maps. Retrieved May 9, 2017.
  10. "Hello, West End Summit. Goodbye, Lake Palmer". The City Paper. October 2, 2012. Archived from the original on December 24, 2016. Retrieved December 24, 2016.
  11. Sichko, Alex (February 12, 2016). "InterContinental Hotels out of Palmer's West End Summit project". Nashville Business Journal. American City Business Journals. Retrieved November 13, 2017.
  12. French, Jen (March 31, 2016). "'Lake Palmer' Drained; Future of West End Summit Unclear". WZTV fox17.com. Nashville, TN: Sinclair Broadcast Group. Retrieved November 13, 2017.
  13. Ashton, Gary (October 21, 2012). "West End Summit No Longer A "Hole" In The Ground". The Ashton Real Estate Group of RE/MAX Advantage. Archived from the original on December 24, 2016. Retrieved December 24, 2016.
  14. Lawson, Richard (November 8, 2008). "Contractor sues West End Summit backers". Nashville Post. Retrieved December 24, 2016.
  15. McCarthy, Sarah (27 March 2018). "Lake Palmer Sold to Alabama Developer". WTVF. Retrieved 2 May 2018.
  16. Godwin, Brent (March 28, 2018). "Alabama real estate firm to lead massive Nashville development". Birmingham Business Journal. American City Business Journals. Retrieved May 4, 2018.
  17. Williams, William (March 26, 2018). "WES site buyer offers few clues as to future development". Nashville Post. Retrieved 2 May 2018.
  18. Sichko, Adam (August 24, 2018). "$500M towers to fill a whole". Nashville Business Journal. American City Business Journals. p. 8. Retrieved 29 August 2018.
  19. "'Lake Palmer' Development Set To Begin This Fall". WTVF. 29 August 2018. Retrieved 29 August 2018.
  20. Sichko, Adam (May 3, 2019). "His Ace in the Hole: Cash in Hand". Nashville Business Journal. pp. 4–7. Retrieved 10 May 2019.





Текст в блоке "Читать" взят с сайта "Википедия" и доступен по лицензии Creative Commons Attribution-ShareAlike; в отдельных случаях могут действовать дополнительные условия.

Другой контент может иметь иную лицензию. Перед использованием материалов сайта WikiSort.org внимательно изучите правила лицензирования конкретных элементов наполнения сайта.

2019-2024
WikiSort.org - проект по пересортировке и дополнению контента Википедии